Shimla: Delay in 100 MW hydro project led to cost overrun of Rs 643 cr, says CAG

The project was scheduled to be completed by March 2015 with an estimated cost of Rs 676.29 crore, but the same was commissioned in September 2017 at a cost of Rs 1,319.33 crore